Scroll down to find the latest updates on:
Rooted in Hope, Westwood Early Childhood Center, and local road construction closures.

Rooted in Hope Projects

Updated as of July 28, 2026:

 

The summer heat and construction are upon us — planning ahead has kept us cool!

Here's a summary of active and upcoming projects on the Westwood campus:​

  • New Rooftop Mechanical Unit: The week of July 13, the old unit stopped cooling. Our technicians determined the compressor was failing and would not work much longer, or cool effectively during the heat wave. Luckily, the new unit was in town! The HVAC contractor mobilized their troops and scheduled a crane for Thursday, and by Friday afternoon the unit was installed and cooling! Our planning paid off, helping us avoid an emergency unit replacement.

  • Sanctuary Air Handler Replacement Work: Demolition work begins August 3. The new Sanctuary system will be operational within three weeks.                                                        There will be NO AIR CONDITIONING DURING WORSHIP ON AUG. 9 & 16!

  • Welcome Center at Door #2: construction is complete! Within a few weeks, staff and volunteers will be fully transitioned into the new space.  

  • New Security Door: the new wood-frame and glass security door will be installed in August near the Welcome Center. After installation, our safety and security vendor will install the door controls that connect it to the rest of our system. The Welcome Center and security door processes and training will be established over a few months before a formal go-live.

  • Door 3 (west side): will be replaced in mid-August; this should be a 1-2 day turnaround.

​

Please use caution when on campus, as construction is underway both inside and outside the building. We will do our best to keep you informed of notable updates. Thank you for your patience and flexibility as we work through these exciting projects together!

​

Detailed monthly updates are available in the E-News.​​

Woven in a Culture of Grace - Lent 2025 (final v6) (500 x 500 px) (1).png

Westwood Early Childhood Center (WECC)

Updated as of July 28, 2026:

​

​​WECC classroom renovations and updates are being completed!

As a reminder, the purpose of this project is to update our classrooms, remain in compliance

with NAEYC recommendations, and further strengthen safety and security throughout the building. This project has been thoughtfully planned to make it as smooth as possible for

children, families, and staff. In addition to classroom changes, a major change will be the relocation of the WECC office to the east side of the building, by Door 1, at the end of the project.

 

Projects completed over the last month include:

  • Classroom 14 renovations: a new pre-K classroom. The students moved into their new classroom late July and love the new space. For the first time, all WECC students are together inside our secure classroom areas. Thank you for the flexibility during this time.

  • WECC new security door: the door was moved 20 ft to the east. It is installed and working. The old door frame and wall will be removed at the end of July/beginning of August. The floor will be carpeted to match the rest of the Door 2 entrance area. 

  • Classrooms 16 & 18: work continues with new walls installed and drywall complete. Paint and flooring will begin very soon. This room is scheduled to be completed by mid-August. 

  • Room 23 remodeling: the new WECC offices are complete. Temporarily, this room will serve as extra space for the young toddlers until they move back into their rooms, and then we will use it as a temporary space for the infants when we start remodeling their rooms. The office will be fully converted at the end of the classroom projects.

.  

The project is continuing through the three phases and remains on schedule. 

  • May-June will include: Toddler II, Preschool I, and Pre-K - Completed

  • June–August will include: Toddler I and Pre-K - In progress

  • August–September will include: Infant I and Infant II - Beginning

​

The WECC office is temporarily located in the Fireside Room off the Commons for the duration of the project. In addition to the classroom work, construction will also take place in shared spaces around the church from May through mid-October. ​

image.png

Road Construction

Updated as of July 28, 2026:

​

​​​Access to Westwood Remains Open:

Visit Minnesota DOT or 511mn.org (for up-to-date info and traffic) as the best resource to

verify road closures. The City of St. Louis Park has ongoing details regarding Louisiana Ave. & Cedar Lake Rd. 

​

Click the links below to see details about the specific project, maps, and timelines.

 

Driving to Westwood: Check your route and use detours. As of Monday, July 27, new changes to exits, detours, and closures have begun to/from Hwy 169 & Cedar Lake Rd.

  • Delays and detours remain scheduled through September.​

  • Work on the east leg of Jordan Ave. South in St. Louis Park is scheduled to be completed with access to/from Cedar Lake Rd. via the northbound Hwy 169 ramps reopening on Sun, July 26.

  • Starting Mon, July 27, construction will start on the west leg of Jordan Ave. South in Minnetonka. This work will close Jordan Ave. South between north of the Hwy 169 ramps and Cedar Lake Rd. through September.

​

​

​

  • City of St. Louis Park - Cedar Lake Rd. & Louisiana Ave

    • Review this page for work directly impacting the roads near Westwood.​ The City of SLP posts updates and suggested detours.

    • Contact the city engineers with questions.

​ ​